The
Build
Pre-build
15
September 2004 -
Picked up kit from Flylight.
15
- 17 September
- Checking kit against parts list.
20 September
- Paperwork to register
project sent off via inspector to BMAA
5 October
- Contacted by BMAA
re inspectors "qualifications"
20
October - Inspector visits Flylight to become "qualified".
29
October - Paperwork received back from BMAA giving OK to
start building.
|